FIRST BUILD | 22-ACRE WEST OVERLOOK

DESIGN AND CONSTRUCTION 2024 MILESTONES

Began site preparation with "Demo Day!"

HSP is on pace to accelerate the project in 2025.

Main Street

CAFE

FILTER GARDENS

EVENT CENTER

WATER FACTORY

PICNIC GROVE

TERRACE GARDEN

Successfully obtained City demolition permits and started demo for the West Overlook.

THE SHED

EVENT LAWN

PLAY COVE

Conservation team initiated the plant selection process for the park and vetted the planting list with local conservationists and partners.

Commerce Street

Advanced designs and conducted cost estimates and value-engineering.

Re-assessed economic, health, environmental, and safety impact of updated Park design.

Approved a construction budget based on value-engineered estimates.