Ardmac Ready to go Modular Data Centres w/HAC

 

As part of our continuing design development for manufacture and assembly strategy, Ardmac have developed the ground supported (GS) hot and cold aisle containment solution and the ceiling supported (CS) hot and cold aisle containment solution with our established off-site fabrication techniques.

Off-Site Fabrication / On-Site Assembly

Full height lightweight independent frames and containment walls are manufactured off-site to the agreed scale and dimensions and transported to the specific project location. The off-site fabrication strategy allows for large manageable sections of the framework to be delivered in a ‘flat- pack’ approach and bolted together in-situ for rapid assembly.