Procurement Policy
Tendering Levels Value of contract Procurement Requirements
Responsibility
Up to £1,000
Ensure the cost is value for money
Cost centre owner
£1,000 to £10,000 Two quotations
Cost centre owner
£10,001 to £25,000 £25,001 to £189,329
Three quotations Cost centre owner
Formal tender process
Procurement
Procurement
£189,330 and above
Goods and service - OJEU process applies
£4,733,252 and above
Works - OJEU process applies
Procurement