Timeframes for Tendering Contract Value Procurement Method
Estimated Timescales 1-3 weeks
£0 - £25,000
Purchase Order with the correct quotes obtained in line with the Procurement Policy Invitation to Tender/Request to Quote - formal tender completed with the Procurement Team
£25,000 to £189,330
4-16 weeks
£189,330+ Regulation with Public Contract Regulations
Minimum 16 weeks
Generally most suppliers will be expected to have a contract which will be supported by a Purchase Order in Agresso or Works order (Property). Timing is subject to S20, availability of specifications, knowledge of supplier market etc.