CITY OF DESOTO
Capital Improvement Program FY 2017 - 2021 Street Project Details
Hampton Road Reconstruction
Project Name/No: Project Description: Estimated Start Date:
Construction of water, sewer and paving from Pleasant Run to Belt Line Rd
10/1/2019 9/30/2021
Estimated Completion Date:
Fund:
490
Currently Unfunded. Anticipated issuance of Certificates of Obligation FY2020 thru 2021. Minimal to no operational impact costs. Additional project funding provided in the Water Projects.
Status:
Operating Impact:
Revised: 7/11/16
ESTIMATED EXPENDITURES (000's)
Total Estimated Cost
PY Budgeted
FY
FY
FY
FY
FY
Project Name/Number
Amount
2017-18
2018-19
2019-20
2019-20
2020-21
Hampton Road Reconstruction
$
-
$
3,000
$
-
$
-
$
-
$
1,000
$
2,000
Estimated Amount (000's)
Funding Sources
$
-
$
3,000
Certificate of Obligation Bonds
$
-
$
-
$
-
$
1,000
$
2,000
Made with FlippingBook - Online Brochure Maker