CITY OF DESOTO
Capital Improvement Program FY 2017- 2021 Street Project Details
Parkerville Road Widening (Polk to Hampton Road)
Project Name/No: Project Description:
Widen roadway to a 4-lane divided concrete roadway with underground drainage.
Estimated Start Date:
10/1/2018 9/30/2022
Estimated Completion Date:
Fund:
490
Currently Unfunded. November 2014 Bond Election passed. Anticipated issuance of General Obligation Bonds FY2018 thru 2021. Ongoing operational costs include irrigation, landscaping and lighting at approximately $40k per year.
Status:
Operating Impact:
Revised: 7/11/16
ESTIMATED EXPENDITURES (000's)
Total Estimated Cost
PY Budgeted
FY
FY
FY
FY
FY
Project Name/Number
Amount
2016-17
2017-18
2018-19
2019-20
2020-21
Parkerville Road Widening
$
-
$
6,000
$
-
$
1,000
$
1,000
$
2,000
$
2,000
Estimated Amount (000's)
Funding Sources
$
-
$
6,000
Certificate of Obligation Bonds
$
-
$
1,000
$
1,000
$
2,000
$
2,000
Made with FlippingBook - Online Brochure Maker