SUMMIT GONDOLA INSTALLATION

Step 3:

Raise uprights to vertical, lock base shoes and install centre rail. BOTH RAIL TABS MUST BE SHOWING BELOW LANCES . Rails must be horizontal. Use level to check. DO NOT HAMMER DOWN ON RAIL! USING A SCREWDRIVER BEND BOTH TABS UP AROUND LANCES. Install lower rail... IN SINGLE BACK INSTALLATIONS, THE RAIL TAB OPPOSITE THE BACK SHOULD BE BENT UPWARD TO PREVENT THE RAIL FROM ROLLING.

Lance

Centre Rail

To install rails, hold uprights carefully.

Rail must be in a horizontal position.

All rails must be in a horizontal position.

Rail Tabs - Bend to secure

Upright

Step 4:

Install the back panel. Slide down from top... DO NOT DROP BACKS ONTO THE LOWER RAIL! If run is 8 sections or less, install one back into first and last sections to square before leveling. If gondola is more than 8 sections then additional back(s) will need to be installed in centre of run for additional stability. Stand remaining Uprights in run, installing centre and lower rails between the uprights.

Install back panels from top. DO NOT DROP backs.

WARNING! Never allow framework to stand alone until a back panel is in place. Framework may fall! CENTRE SPANNERS must be installed!

CHALK LINES

9

STMDISPLAYS.COM