F. Review . The Stormwater Administrator shall review the application and determine whether the application complies with the standards of this section in accordance with the following: i. Approval . If the Stormwater Administrator finds that the application complies with the standards of this section, the Stormwater Administrator shall approve the application. The Stormwater Administrator may impose reasonable conditions of approval as needed to ensure compliance with this section. The conditions shall be included as part of the approval. ii. Failure to Comply . If the Stormwater Administrator finds that the application fails to comply with the standards of this section, the Stormwater Administrator shall notify the applicant and shall indicate how the application fails to comply. The applicant shall have an opportunity to submit a revised application.
iii. Revisions & Subsequent Review .
1. Revised Application . A complete revised application shall be reviewed by the Stormwater Administrator after its resubmittal and shall be approved, approved with conditions, or denied.
2. Application Withdrawn . If a revised application is not resubmitted within 120 days from the date the applicant was notified, the application shall be considered withdrawn, and a new submittal for the same or substantially the same project shall be required along with the appropriate submittal fee.
3. Resubmittal without Payment . One (1) resubmittal of a revised application may be submitted without payment of an additional permit review fee. Any
resubmittal after the first resubmittal shall be accompanied by the appropriate submittal fee, as established pursuant to this section.
(3) Review & Approval Schedule. The submittal, review and approval of a stormwater management permit shall be in accordance with the following:
A. Concept Plan & Consultation Meeting . Before a stormwater management permit application is deemed complete, the Stormwater Administrator or developer may request a consultation on a concept plan for the post-construction stormwater management system to be utilized in the proposed development project. This consultation meeting should take place at the time of the preliminary plan of a