CONSTRUCTION SCHEDULE

Custom Home Timeline Goals (34 Week Schedule)

Demolition, Clearing & Excavation - 3 Weeks Footings, Foundation Walls & Slab - 5 Weeks Framing - 4 Weeks Rough Mechanicals & Inspections - 6 Weeks Drywall - 2 Weeks Hardwoods, Trim & Prime Paint - 2 Weeks Cabinets, Tile & Countertops - 3 Weeks Interior Paint & Mechanicals Trim - 2 Weeks Finish Hardwoods & Carpet - 3 Weeks Appliances & Final Inspection (C.O.) - 3 Weeks Orientation and Closing - 1 Week

Timeline is an estimate and is dependent on many factors including weather, labor availability and timeliness of design decisions