MANY ISLANDS PIPE LINES (CANADA) LIMITED EMERGENCY PROCEDURES MANUAL Document Change Control

Document Change Control This table contains a history of the revisions made to this document. The document itself is stored under version control in the Corporate Emergency Management Program (CEMP) SharePoint site. Upon completion of each version of the document, enter a brief description of the change(s) in the table below.

Date of Release

Approved By

Version

Brief Description of Change

Updated By

Updates to contact info, formatting, links, Husky Marwayne land location, and EPZ details

March 2026

March 31, 2026

P. Haubrich

M. McCullough

January 2025

Minor update in 2.2.5 Notification Flowchart

January 2, 2025

A. Saxena

D. Janke

March 2024

Updated Manual Distribution and Maintenance list

March 20, 2024

A. Saxena

D. Janke

Removal of Esther - Smiley Pipeline. Updated Saskatchewan Rail Network map and Contact List.

January 2023

January 23, 2023

B. Boyes

D. Janke

Updates to contact info and pipeline maps, Update emergency levels, update position checklists

April 2022

April 27, 2022

D. Smith

D. Janke

September 2021

Updates to contact information, Section 2.2 and Section 2.4

September 16, 2021

G. Samuelson

D. Janke

June 2021

Addition of Pierceland Supply Project

June 28, 2021

G. Samuelson

D. Janke

March 2021

Regular review and updates to contact information.

March 31, 2021

G. Samuelson

D. Janke

Updated emergency contacts and pipeline maps. Added Shaunavon Interconnect. Updated government notification requirements and acronyms. Updates to document format and re-organization of relevant sections. Removed Chinook – Loomis pipeline.

V. Kreklewetz- Smyth

October 2020

October 5, 2020

D. Janke

March 2020

March 30, 2020

D. Janke

R. Greggains

July 2019

Inclusion of Husky Marwayne deactivation.

June 26, 2019

G. Samuelson

D. Janke

Updated Distribution List, Key Contacts, Spill Response and Emergency Response Guidelines. Removal of Renaissance – Bronson North Pipeline. Added information related to full scale exercise and Provincial EOC. Updated NEB/TSB reporting procedures, ICS figures and Key Contacts List. Removal of Petrolia Pipeline. Updated Key Contacts List.

June 2019

June 7, 2019

G. Samuelson

D. Janke

February 18, 2019

February 2019

D. Janke

R. Greggains

December 2018

December 14, 2018

D. Janke

R. Greggains

Addition of Portal Municipal Gas Pipeline. Updated Key Contacts List.

October 2018

October 16, 2018

D. Janke

R. Greggains

September 2018

Regular review and update to contact information. Addition of Macklin Compressor Station. Removed 10 and 11 Pipelines: Mid-Continent NPS 16 & Mid-Continent NPS 24 and updated. Husky Marwayne deactivation. Regular review and update to contact information. Inclusion of relevant emergency management information for the purpose of public posting. Regular review and update to contact information. Inclusion of relevant Construction Operations Maintenance Practices into the manual.

September 27, 2018

D. Janke

R. Greggains

September 2017

September 1, 2017

D. Janke

August 2017

August 15, 2017

D. Janke

September 27, 2016

August 2016

D. Janke

March 2016

Regular review and updates to contact information.

March 17, 2016

D. Janke

May 2015

Regular review and updates to contact information.

May 2015

T. Danielson

Information has been redacted throughout this document in accordance with noted regulations and legislation. For more information, please contact us at privacy@saskenergy.com.

Made with FlippingBook Ebook Creator