PROJECT INFORMATION

• Company entering: Zutari • Client: Rand Merchant Bank • End date: 31 July 2021 • Main Contractor: Trencon Construction • Consulting Engineer: Zutari (Civil, Structural, Wet services and Green Star Consultant) • Architect: Boogertman + Partners Architects • Project Manager: Metrum Project Management • Quantity Surveyors: Vusela Quantity Surveyors • Electrical Engineer: Claassen Auret • Mechanical Engineer: Adaptive Resource Engineers • Fire Engineer: Chimera Fire Protection Consultants

timeously with the quantity surveyors, project managers, the client and the rest of the consulting team. This ensured that the structural works were coordinated, there was sufficient allowance in the budget, and the programme allowed for the complexities of the project. 

95

21 st Best Project Awards 2022