Do not scale the drawing. Use figured dimensions in all cases. Check all dimensions on site. Report any discrepancies in writing to Haskoll before proceeding.
Scale Bar (m)
0
1
2
4
8
SPECIFICATION
Indicates new lining and linear 150mm wide drainage channel to edge of slab filled with pea shingle and perforated land drain.
Key
Note:
Glazed frontage Contractor to check and measure each arch opening prior to shopfront manufacture or infill. Due to the nature of arch construction and varying floor levels, arch openings width and height may vary between arches. Dimensions shown on drawings are approximate.
Fully refurbished
Indicates new lining and linear 150mm wide drainage channel to edge of slab filled with pea shingle and perforated land drain.
GLAZED FRONTAGE
GLAZED FRONTAGE
GLAZED FRONTAGE
Electric roller shutters
Note:
WC facility
Contractor to check and measure each arch opening prior to shopfront manufacture or infill. Due to the nature of arch construction and varying floor levels, arch openings width and height may vary between arches. Dimensions shown on drawings are approximate.
UNIT 88 c. 1,400 SQ FT
UNIT 89 c. 1,400 SQ FT
UNIT 91 c. 1,400 SQ FT
LED lighting
Good ceiling height
.
Great location
24/7 access
WC
Note: Toilet block to be provided by tenant.
WC
WC
WNO JRI
19/01/23
P6 Updated drawings & annotations
ALO JRI
13/01/23
P5 Stage 4 Updates
ALO TWE 13/12/22
P4 Stage 4 Updates
ALO TWE 18/11/22
P3 Stage 3 Updates
ALO ACA 28/09/22
P2 Planning
FIRE DOOR
FIRE DOOR
.
ALO ACA 22/09/22
P1 First Internal Issue
Rev
Description
Drawn Checked Date
Suitability
Information
Project
The Arch Company Tiverton - Taco Tiverton, London
Drawing
Proposed GA Level 00 Plan
Note: Toilet block to be provided by tenant.
WNO JRI
19/01/23
P6 Updated drawings & annotations
P5 Stage 4 Updates Drawing Number
ALO JRI
13/01/23
Project ID
Originator Zone Level
Type Role Number
ALO TWE 13/12/22 RYD 00 00 DR A 3051 - - - - -
P4 Stage 4 Updates
TITAC
-
ALO TWE 18/11/22
P3 Stage 3 Updates
Project Number
Scale at
A1
Status
Revision
ALO ACA 28/09/22
P2 Planning
4600-36
S4
P6
As indicated
ALO ACA 22/09/22
P1 First Internal Issue
Rev
Description
Drawn Checked Date
Suitability
Information
Project
The Arch Company Tiverton - Taco Tiverton, London
Drawing
Proposed GA Level 00 Plan
Drawing Number
Project ID
Originator Zone Level
Type Role Number
TITAC
-
- RYD 00 00 DR A 3051 - - - -
Project Number
Scale at
A1
Status
Revision
4600-36
S4
P6
As indicated