Building the stream pipe
Installing french mattress
After installing stream crossing
PROJECT SUMMARY AND RESULTS The project included replacing a three-foot stream pipe on an unnamed tributary to South Branch Two Lick Creek with a 14-foot box culvert, improving a wetland crossing pipe with a four-foot squash pipe (previously 24 inches), and installing a 158 square yard French mattress in between the two. Green Township also worked with the adjacent landowner in order to install three stabilization structures for high flow events.
FUNDING SOURCES AND PROJECT COSTS $112,872.34 — ICCD Dirt & Gravel Road grant funds $1,097 – Green Township in-kind contributions