Hiranandani Fortune City | Newsletter - March 2020

Project: Vesta

RCC slab completed till slab 30

Block works completed till slab 25

Concealed MEP works completed till slab 22

Waterproong works completed till slab 19

The above-mentioned data holds true as on February 2020