SUPPLY CHAIN TRANSFORMATION: GUIDE FOR SUPPLIERS

FREETOWN GROCERY VENDOR TIMELINE

DEPARTMENT

TIMELINE

TASK

Data Validation

July 2020

Data validation begins

EDI / B2B

July 2020

EDI setup begins

Network Optimization

August 2020

Inventory flow path and demand impacts communicated

Vendor discussions on current freight rates, transition plan and CPU agreements

Logistics

October 2020

EDI / B2B

October 2020

EDI setup complete

Data Validation

November 2020

Data validation complete

EDI / B2B

Cascading Process

All Item PO Test

Accounting

November 2020

Vendors needing new vendor #s identified

EDI / B2B

Cascading Process

BICEPS PO/Invoice Test

E2E testing; 25 vendor test only *Tests the overall accounting transaction flow

EDI / B2B

Cascading Process

Accounting

December 2020

Vendor responses for new vendor setup sent

EDI / B2B

December 2020

EDI testing and go-live readiness complete

Relevant Efficiency Program discussions complete. Efficiency.programs@adusaprocurement.com

Efficiency Programs

January 2021

Logistics

January 2021

Vendor inbound CPU agreements due back

GO-LIVE DATE: Feb. 28, 2021

Go Time! ADUSA Distribution POs start to land at DC