2021 SDP Transformation Tool Kit

21

SUPPLY CHAIN TRANSFORMATION: GUIDE FOR SUPPLIERS

FREETOWN FRESH VENDOR TIMELINE

DEPARTMENT

TIMELINE

TASK

Data Validation

September 2020

Data validation begins

EDI / B2B

September 2020

EDI setup begins

Network Optimization

November 2020

Inventory flow path and demand impacts communicated

Vendor discussions on current freight rates, transition plan and CPU agreements

Logistics

January 2021

Data Validation

January 2021

Data validation complete

EDI / B2B

January 2021

EDI setup complete

EDI / B2B

Cascading Process

All Item PO Test

Accounting

February 2021

Vendors needing new vendor #s identified

EDI / B2B

Cascading Process

BICEPS PO/Invoice Test

E2E testing; 25 vendor test only *Tests the overall accounting transaction flow

EDI / B2B

Cascading Process

EDI / B2B

February 2021

EDI testing and go-live readiness complete

Accounting

March 2021

Vendor responses for new vendor setup sent

Relevant Efficiency Program discussions complete. Efficiency.programs@adusaprocurement.com

Efficiency Programs

March 2021

Logistics

April 2021

Vendor inbound CPU agreements due back

GO-LIVE DATE: May 2, 2021

Go Time! ADUSA Distribution POs start to land at DC

VENDORS SHOULD REFERENCE THE TRANSFORMATION CHECKLIST ON P. 14 OF THIS GUIDE TO ENSURE THAT ALL CRITICAL STEPS FOR TRANSITION ARE COMPLETE ON THE CORRECT TIMELINE.