Central Washington University CHCI Assessment Report 12-10-13
ADA parking designated for the CHCI includes 1 space in the rear parking lot. It is appropriately signed by not stripped for accessible parking. Parking Layout, Striping and Signage A concrete sidewalk is provided at the north entrance to the building. This entrance is for staff only. An asphalt sidewalk is provided from the parking area to the main public entrance. At the entrance, the paving switches to interlocking pavers with concrete framing. Generally this provides a compliant accessible route of travel. Sidewalks
LANDSCAPING
The site has fully-developed and mature landscaping consisting of groundcover, lawn, trees, and feature planting/flowers. It is well cared-for and appropriate for the use/site. Plantings
Planting areas around the building and in the outdoor care areas appears to have a functioning and functional irrigation system. Irrigation