New Residence Hall - Proposal

5.) PROJECT TIMELINE Anticipated Project Design and Construction Schedule

Activity

Status as of 10/19/17

Date

Project Review Committee DB Public Meeting

Complete

September 28, 2017

Project Review Committee DB Notice Letter

Complete

October 12, 2017

CWU Advertise & Issue DB Team RFQ

In progress

October 17, 2017

Statements of Qualifications (SOQ) Due

November 07, 2017

SOQ Scoring and Finalists Selection

November 14, 2017

CWU Issue Request for Proposals

November 16, 2017

Proposal Finalists’ Exchanges with Owner

December 07, 2017

Proposals Due

December 19, 2017

Highest Scored Finalist Notification

December 28, 2017

Notice To Proceed

January 08, 2018

Design Initiation

January 09, 2018

Building Permit Documents

April 15, 2018

Construction Initiation

May 01, 2018

Substantial Completion

June 01, 2019

Owner Occupied – Final Completion

August 02, 2019