Executive Summary - 6 year plan and fiscal year budget upda…

Recreation Expansion - Proposal

October 24 October 25

Recreation Expansion Usage Sub-Committee

Recreation Expansion & Tomlinson Committee Meeting RFQ Awarded Academic Meeting with Dr. Pellet and Dean Ballard

October 25 October 31 November 1 November 2 November 3

Recreation Expansion Usage Sub-Committee

Recreation Expansion & Tomlinson Committee Meeting

Board of Trustee Presentation Board of Trustee Presentation

November 3-17

Pre-Design

November 20 - December 22

Schematic Design

December 25 - January 26, 2018

Design Development

January 29 - March 2,

Construction Document

March 5 - March 30,

Permitting

April 2 - April 27

Bidding

April 30 – August 30

Construction Administration

September 10

Substantial Completion