As noted in Table 3-1 the Town is in the process of renovating a portion of the Centre including the main entrance to the Community building, the pool area and amenities, and common areas. The architectural concept plan notes the following: Lower Level • New entry + change rooms (+/- 5,400 sf) • Existing pool: new b/f pool ramp + deck resurfacing (+/- 7,830 sf) • Existing change rooms + pool office renovation (+/- 3,000 sf) • Health club: removal of existing washrooms + sauna (+/- 540 sf) Upper Level • Accessible pool viewing renovation (200 sf) • Multi-purpose room (approx. 390 sf) The space/room areas indicated above reflect both additions to the existing structure and internal changes to repurpose/ upgrade existing spaces that begin to address some of the building’s deficiencies related to accessibility and current/future program needs. The newly renovated portion of the building is anticipated to re-open in the fall of 2024. At that time, the Town can resolve the reported issue of