Foreword:
FY25 provided an opportunity for the new Facilities team to get more familiar with operational needs around the district and experience a complete year in their roles. Throughout FY25, the facilities team continues to: (1) maintain facilities in good working order, (2) address facility emergency situations, and (3) provide oversight of the CIP Plan.
This memo is intended to provide:
- An overview of the status of the District’s 13-year Capital Improvement Program (CIP) plan, now its sixth year, with some updated guidance based on a Facility Condition Assessment conducted during FY23 - A summary of several capital projects completed and/or underway in FY25. - A summary of Proposed FY26 CIP Projects
Overview–CIP Status:
During the first five years of the CIP plan, the summary of capital financial activities, include project funding and expenditures as is follows:
Funding Sources:
CIP Bond (March, 2020) Budget Appropriations
$7,500,000
FY2020 FY2021 FY2022 FY2023 FY2024
$1,198,100
$0
(Funding Deferred)
$345,250 $501,500 $550,000
$2,594,850 $10,094,850
Available resources for Capital Projects
Expended on projects through FY2024
$10,071,025
CIP Fund Balance as of June 30, 2024
$23,825