LCI Preconstruction & Estimating Training Manual

Scope Recap Report

16001 Electrical-Building

.

16-2596 300 West Huron 300 West Huron Chicago, IL

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

1

2

3

4

5

6

Contact Phone #

Contact Phone #

Contact Phone #

Contact Phone #

Contact Phone #

Contact Phone #

ESTIMATE

Company Name

Company Name

Company Name

Company Name

Company Name

Company Name

ITEM BREAKDOWN

Qty.

Unit Price

Total

Area

Main Mechanical ( pent House level) Panel- 1200A Main Core & Amenities Panel- 1000A

1 1 1

EA $12,500.00 EA $10,500.00 ALLOW $20,000.00

$12,500 $10,500 $20,000

CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS

Disconnect Switches

Transformers

Transformers-30 KVA Transformers-300 KVA Transformers-112.5 KVA

1 1 1

EA $2,800.00 EA $6,340.00 EA $5,340.00

$2,800 $6,340 $5,340

Building Service

Prim. Service Empty Conduit from ComEd Vault to the Building- 5"

0 1 1 6 1

LF

$300.00

MCC - 3000 A 480/277V MCC - 4000 A 208/120V Meter Bank for residential

LS $120,000.00 $120,000 LS $145,000.00 $145,000

ea $14,500.00

$87,000 $8,500

Meter Bank for residential Pent house

ea

$8,500.00

Motor Controls

Mechanical /Equipment branch conduit

$28,800 $13,300

1 1

ALLOW $28,800.00 ALLOW $13,300.00

VFD receive and Install

Disconnect Switches Disconnect Switches

CS CS

1

ALLOW $13,720.00

$13,720

Feeders

CS CS

Buss Duct riser- 2000 Amps

665

LF

$475.00

$315,875

Mechanical Equipment Feeder - 1200 A -480 Feeder Distribution Wiring with Mechanical room ( 1st floor)

433

LF

$340.00

$147,220

CS

0 0 0

LF LF LF

$400.00 $400.00 $400.00

CS CS CS

Feeder for Make up Air unit

Feeder for Back of the house panel

Distribution wiring within electrical room ( per floor)

0 0

LF LF

$400.00

CS CS

Feeder for each Unit -HP

$8.00