LCI Preconstruction & Estimating Training Manual

Scope Recap Report

16001 Electrical-Building

.

16-2596 300 West Huron 300 West Huron Chicago, IL

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

1

2

3

4

5

6

Contact Phone #

Contact Phone #

Contact Phone #

Contact Phone #

Contact Phone #

Contact Phone #

ESTIMATE

Company Name

Company Name

Company Name

Company Name

Company Name

Company Name

ITEM BREAKDOWN

Qty.

Unit Price

Total

Area

Misc Feeders ( exhaust fans etc )

0

LF

$8.00

CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS CS

Elevator

Elevator Feeder- (Riser) and horizontal runs - 200 Amps

450

LF

$60.00

$27,000 $7,600 $2,800

Elev. DP & disconnect

2 1

EA $3,800.00 EA $2,800.00

Transformers

Exterior Lighting/Canopy Lighting Building Exterior Lights - allowance

$40,000 $3,900

20

EA $2,000.00

Wire and conduit

600

LF

$6.50

MDF Room

Lighting with switch

25

EA $310.00 EA $1,052.50

$7,750

Power distribution each floor

750

$789,375 $20,150

Empty - 2" conduit

1,300

EA

$15.50

Emergency System(Generator)- Separate Break out

Natural Gas Generator 300KW

0 0 0 0 0

EA EA EA

Gen DP - Panel-

ATS- switches(Qty = 1)

Fire Pump Feed - (double Feed )

ALLOW

(208/120V) EM/Panels

EA

Public Restrooms

Power

Reg. Power Outlets GFI. Power Outlets Switches with sensors

0 0 0 0 0

EA $120.00 EA $135.00 EA $120.00

Connection for electric unit heaters etc

EA LF

$55.00

Wiring and Conduit

$6.00

Lighting

Lighting Allowance Wiring and Conduit

0 0

Allow $13,000.00

LF

$6.00

Div 16 Return to Table of Contents