LCI #16-2596 - 300 West Huron April 4, 2016 Page 7 of 17
Division 3 Cast-in-Place Concrete 1.
Scope features all concrete building substructure and superstructure above caissons, including caisson caps, grade beams, exterior basement walls, stairs and retention wall at southeast corner, shear walls, slab on grade, elevator pit, parking ramp, elevated slabs, columns, stairs/landings, concrete parapet and barrier walls at parking levels. 2. The structure is to be a post-tensioned slab system. 3. Please note that on the 3 rd floor below the amenities podium, the documents indicate large 60” x 96” transfer beams. The clear height for a vehicle traveling underneath this transfer beam is 6’. 4. On the north elevation, material keynote 8 states “Exposed pre-cast concrete”. Our bid is based upon this being poured in place concrete slab and up turned slab/crash wall. We exclude pre-cast concrete. 5. We have included a running track coating and three lines of striping. 6. We assume no camber of post tensioned deck to due sizing of bays. 7. Staining of underside of terraces/balconies. Division 4 Masonry 1. Stone panels based upon 1.5” x 2’ x 4’ Indiana limestone with a buffed finish. 2. 8” CMU with a parge coat has been figured for key note 11, “concrete masonry units”. We have not included fiber cement siding. 3. We have included the granite curb at the bottom of the storefront. 4. We have included concrete block walls at the following 1 st floor back of house areas: water service, generator, ComEd vault, trash room, electrical room, ATS room, retail trash and janitor. 5. We have included concrete block walls at Stair No. 3.
Division 5 Miscellaneous Metals 1.
Elevator hoist/divider beams
2. 3. 4. 5. 6.
Elevator pit ladders
Roof ladder
Elevator sump pit cover. Dock angles for equipment. Steel clips at top of CMU walls
7. We have included an $85,000 structural steel allowance for 25 th
floor mechanical screen.
8. 9.
Light steel tube frame behind stone panels.
Railings at planters at 4 th
floor.
10. Metal railings at stair wells.
Division 6 Rough Carpentry 1. We include in wall blocking at the following locations: a. All wall hung millwork and cabinetry b. All wall hung toilet accessories c. At shower doors d. Bike racks e. Window treatment pocket locations 2. We include fire treated plywood at the IT Closets on all floors. 3. Roof blocking at the 25 th floor.