Existing Utilities & Requirement Matrix
Code Compliance Requirements
7 Story Building- 2004 design
High Rise Code Compliance
Comments
NO Services
Existing
4 Story Building
7 story Building
Per design we will provide 3 elevators for garage and 3 passenger elevators for office building serving all 4 floors, One Freight elevator for office
Per design we will provide 3 elevators for garage and 4 passenger elevators for office building serving all 7 floors
Per design we will provide 3 elevators for garage and 4 passenger elevators for office building serving all 7 floors
1
Elevator
building
NA
No Issues
Visual inspection was done by LCI & Plumber Visual inspection was done by LCI & Plumber
2
fine with existing connection
Storm Water
8"
NA
8"
fine with existing Connection No Issues
3
Sanitary
8"
NA
8"
fine with existing connection fine with existing connection No Issues
No provision for central kitchen or retail needs
4
Water Main
NA
10" with existing booster pump Larger booster pump
Larger booster pump
10"
No Issues
we need stand pipe , UP size the pump to 1500gpm, Note : may need to upsize the Fire Main from 6 to 8 inch
existing pump can serve additional garage Plus four story office
we have 6 " main ., we may need 8" main ( still waiting for final calculations from sub)
500 GPM Pump serving existing Garage
we need stand pipe , UP size the pump to 1500gpm,
stand pipe , fire dept connection on roof
NA
5
Fire Protection
Need Increase in One pipe size Vertical run -6"
Need Increase in One pipe size Vertical run -6"
NA
1) Per Drawings-4"
NA
No Issues
We are excluding any and all scope for work for central kitchen , or retail / restaurant needs.
Need to UP Size (4 story design) Water Heaters (for additional fixture counts ) Replace the booster pump with 95 feet head
Need to UP Size (4 story design) Water Heaters (for additional fixture counts ) Replace the booster pump with 95 feet head No need of any booster pump because all major equipment location (in garage basement) Other than Smoke evacuation system , rest of the building design works
Plumbing
Per design Domestic water heater should be fine
Water Heater
Small water heater for garage only
No Issues
New booster pump for 4 story
Small Booster only for garage
6
Booster Pump
No Issues
we have 6"Natural Gas coming from Garage basement to office building
we need to check pressure , We may have to add small booster pump
same as existing condition
7
No Issues
No Issues
Natural Gas
All the equipment selection is based on New energy code requirements
Make up air unit for garage, exhaust fans and unit heaters
We need Smoke evacuation for 4 story building
We need to up size boilers ,and add Smoke evacuation
For garage there is no issue
8
Smoke evacuation
HVAC
We need 4000A service for Building , design shows 3000A, we have to include fire alarm system for High Rise & 250KW Generator
For garage 1200 A, will cover, we are carrying allowance for some existing code compliance items, NO Generator
Up size the Service to 6000 A,and Fire alarm for high rise, and 500 KW Generator
Up size the Service to 6000 A,and Fire alarm for high rise, and 500 KW Generator
Garage have 1200 A
Fire alarm Per High Rise codes & Generator
9
Electrical
Per code ,we need Generator , because of fire pump
No Generator
Add 250 KW Generator (Natural )
Per design 500 KW Gen
Per design 500 KW Gen
10
No Issues
Generator
We have allowance for empty conduit We have allowance for empty conduit
We have allowance for empty conduit We have allowance for empty conduit
We have allowance for empty conduit We have allowance for empty conduit
No service
11
Not Required
No Issues
Telephone
No service
12 Data - Fiber
Not Required
No Issues
Return to Table of Contents
Made with FlippingBook flipbook maker