LCI Preconstruction & Estimating Training Manual

Activity ID

Orig Dur

Early Start

Early Finish

2013

2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015

Description

OCT

NOV

DEC

19th Floor Finish Selection

113635 19th Floor Finish Selections

0

10JUN15

20th Floor Finish Selections

113645 20th Floor Finish Selections

0

15JUN15

21st Floor Finish Selections

113655 21st Floor Finish Selections

0

18JUN15

22nd Floor Finish Selections

113665 22nd Floor Finish Selections

0

22JUN15

23rd Floor Finish Selections

113675 23rd Floor Finish Selections

0

24JUN15

SITE IMPROVEMENTS

Interior/Site Demolition

042313 Interior/Site Demolition

30 20JAN14 A 03MAR14 A

Utility Disconnects for Demolition

042323 Utility Disconnects for Demolition

5 20JAN14 A 24JAN14 A

ComED Relocation

042343 ComED Relocation

30 05MAY14 A 30MAY14 A

Deadline for ComED Relo/Begin Vertical Construct

042353 Deadline for ComED Relo/Begin Vertical Construct

0

30MAY14 A

LCI Mobilization On-Site

042303 LCI Mobilization On-Site

0

22SEP14 A

Relocate City Services (Lights/Signals/Bus Servi

042312 Relocate City Services (Lights/Signals/Bus Servi

5 23SEP14 A 24SEP14 A

Property Survey & Baseline / Benchmark Layout

042327 Property Survey & Baseline / Benchmark Layout

3 23SEP14 A 26SEP14 A

Temporary Utilities - Office

042333 Temporary Utilities - Office

5 24SEP14 A 27OCT14 A

Temporary Sidewalk Barriers

042324 Temporary Sidewalk Barriers

4 30SEP14 A 03OCT14 A

Temporary Fence

042321 Temporary Fence

3 01OCT14 A 03OCT14 A

Natural Gas Line to the Site - BY OWNER

042337 Natural Gas Line to the Site - BY OWNER

0

26NOV14 A

Install Signage

042369 Install Signage

3 19JAN16

21JAN16

Site Concrete (Curbs/Gutter/S

042339 Site Concrete (Curbs/Gutter/Sidewalk/Pads)

3 20JAN16

22JAN16

Site Electrical

042345 Site Electrical

5 20JAN16

26JAN16

Install Pavers

042354 Install Pavers

4 20JAN16

25JAN16

Site Landscaping

042348 Site Landscaping

4 22JAN16

27JAN16

Asphalt Paving/Patching

042336 Asphalt Paving/Patching

2 25JAN16

26JAN16

Install Fencing

042351 Install Fencing

2 26JAN16

27JAN16

UNDERGROUND

Date

Revision

Checked Approved RAV PCC RAV PCC RAV PCC

Early bar Progress bar Critical bar Summary bar

31JAN15 23FEB15 28FEB15 08APR15

GMP Schedule GMP Schedule GMP Schedule GMP Update #7

ELM & STATE RESIDENTIAL

EXHIBIT C Construction Schedule

MJL

DE

Start milestone point Finish milestone point

Return to Table of Contents

Made with FlippingBook flipbook maker