Activity ID
Orig Dur
Early Start
Early Finish
2013
2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015
Description
OCT
NOV
DEC
Establish COM-ED Temp Powe
042440 Establish COM-ED Temp Power
80 27JUN14 A 05MAY15
Potholing for Caissons
052401 Potholing for Caissons
10 02OCT14 A 15OCT14 A
Probing - at CTA Caissons
052411 Probing - at CTA Caissons
3 13OCT14 A 17OCT14 A
Install Caissons
052410 Install Caissons
19 17OCT14 A 17NOV14 A
Install Gas Lines/NICOR
042430 Install Gas Lines/NICOR
20 10NOV14 A 26NOV14 A
Install Sheeting
052475 Install Sheeting
17 20NOV14 A 29DEC14 A
Excavation for Bsmt/GB's/Foundation/Sheeting
052425 Excavation for Bsmt/GB's/Foundation/Sheeting
35 11DEC14 A 21JAN15 A
Bsmt/GB's/Foundation(Prior to Accident)
052430 Bsmt/GB's/Foundation(Prior to Accident)
32 30DEC14 A 30JAN15 A
Install Crane Pad
052455 Install Crane Pad
5 31DEC14 A 21JAN15 A
WEATHER DELAY #1 - (Extreme Cold)
052480 WEATHER DELAY #1 - (Extreme Cold)
0
05JAN15 A
WEATHER DELAY #2 - (Extreme Cold)
052490 WEATHER DELAY #2 - (Extreme Cold)
0
07JAN15 A
WEATHER DELAY #3 - (Extreme Cold)
052500 WEATHER DELAY #3 - (Extreme Cold)
0
08JAN15 A
Install Underground Electrical
042415 Install Underground Electrical
10 12JAN15 A 31MAR15 A
Tower Crane Pad Cure
052460 Tower Crane Pad Cure
10 21JAN15 A 24JAN15 A
Install Tower Crane
052465 Install Tower Crane
5 25JAN15 A 02FEB15 A
Crane Accident
052485 Crane Accident
6 02FEB15 A 10FEB15 A
WEATHER DELAY #4 - (Blizzard)
052505 WEATHER DELAY #4 - (Blizzard)
0
02FEB15 A
Sewer Stub to PL
042420 Sewer Stub to PL
8 09FEB15 A 21FEB15 A
Basement/GB/Spread Footings/Foundations
052495 Basement/GB/Spread Footings/Foundations
13 10FEB15 A 21MAR15 A
WEATHER DELAY #5 - (Extreme Cold)
052515 WEATHER DELAY #5 - (Extreme Cold)
0
18FEB15 A
Foundation Insulation / Waterproofing
052435 Foundation Insulation / Waterproofing
35 19FEB15 A 21MAR15 A
Foundation Backfill
052440 Foundation Backfill
35 19FEB15 A 17APR15
WEATHER DELAY #6 - (Extreme Cold)
052525 WEATHER DELAY #6 - (Extreme Cold)
0
19FEB15 A
WEATHER DELAY #7 - (Extreme Cold)
052535 WEATHER DELAY #7 - (Extreme Cold)
0
20FEB15 A
WEATHER DELAY #8 - (Extreme Cold)
042435 WEATHER DELAY #8 - (Extreme Cold)
0
23FEB15 A
Install Triple Basin
042425 Install Triple Basin
2 02MAR15 A 17MAR15 A
Date
Revision
Checked Approved RAV PCC RAV PCC RAV PCC
Early bar Progress bar Critical bar Summary bar
31JAN15 23FEB15 28FEB15 08APR15
GMP Schedule GMP Schedule GMP Schedule GMP Update #7
ELM & STATE RESIDENTIAL
EXHIBIT C Construction Schedule
MJL
DE
Start milestone point Finish milestone point
Return to Table of Contents
Made with FlippingBook flipbook maker