LCI Preconstruction & Estimating Training Manual

Activity ID

Orig Dur

Early Start

Early Finish

2013

2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015

Description

OCT

NOV

DEC

Establish COM-ED Temp Powe

042440 Establish COM-ED Temp Power

80 27JUN14 A 05MAY15

Potholing for Caissons

052401 Potholing for Caissons

10 02OCT14 A 15OCT14 A

Probing - at CTA Caissons

052411 Probing - at CTA Caissons

3 13OCT14 A 17OCT14 A

Install Caissons

052410 Install Caissons

19 17OCT14 A 17NOV14 A

Install Gas Lines/NICOR

042430 Install Gas Lines/NICOR

20 10NOV14 A 26NOV14 A

Install Sheeting

052475 Install Sheeting

17 20NOV14 A 29DEC14 A

Excavation for Bsmt/GB's/Foundation/Sheeting

052425 Excavation for Bsmt/GB's/Foundation/Sheeting

35 11DEC14 A 21JAN15 A

Bsmt/GB's/Foundation(Prior to Accident)

052430 Bsmt/GB's/Foundation(Prior to Accident)

32 30DEC14 A 30JAN15 A

Install Crane Pad

052455 Install Crane Pad

5 31DEC14 A 21JAN15 A

WEATHER DELAY #1 - (Extreme Cold)

052480 WEATHER DELAY #1 - (Extreme Cold)

0

05JAN15 A

WEATHER DELAY #2 - (Extreme Cold)

052490 WEATHER DELAY #2 - (Extreme Cold)

0

07JAN15 A

WEATHER DELAY #3 - (Extreme Cold)

052500 WEATHER DELAY #3 - (Extreme Cold)

0

08JAN15 A

Install Underground Electrical

042415 Install Underground Electrical

10 12JAN15 A 31MAR15 A

Tower Crane Pad Cure

052460 Tower Crane Pad Cure

10 21JAN15 A 24JAN15 A

Install Tower Crane

052465 Install Tower Crane

5 25JAN15 A 02FEB15 A

Crane Accident

052485 Crane Accident

6 02FEB15 A 10FEB15 A

WEATHER DELAY #4 - (Blizzard)

052505 WEATHER DELAY #4 - (Blizzard)

0

02FEB15 A

Sewer Stub to PL

042420 Sewer Stub to PL

8 09FEB15 A 21FEB15 A

Basement/GB/Spread Footings/Foundations

052495 Basement/GB/Spread Footings/Foundations

13 10FEB15 A 21MAR15 A

WEATHER DELAY #5 - (Extreme Cold)

052515 WEATHER DELAY #5 - (Extreme Cold)

0

18FEB15 A

Foundation Insulation / Waterproofing

052435 Foundation Insulation / Waterproofing

35 19FEB15 A 21MAR15 A

Foundation Backfill

052440 Foundation Backfill

35 19FEB15 A 17APR15

WEATHER DELAY #6 - (Extreme Cold)

052525 WEATHER DELAY #6 - (Extreme Cold)

0

19FEB15 A

WEATHER DELAY #7 - (Extreme Cold)

052535 WEATHER DELAY #7 - (Extreme Cold)

0

20FEB15 A

WEATHER DELAY #8 - (Extreme Cold)

042435 WEATHER DELAY #8 - (Extreme Cold)

0

23FEB15 A

Install Triple Basin

042425 Install Triple Basin

2 02MAR15 A 17MAR15 A

Date

Revision

Checked Approved RAV PCC RAV PCC RAV PCC

Early bar Progress bar Critical bar Summary bar

31JAN15 23FEB15 28FEB15 08APR15

GMP Schedule GMP Schedule GMP Schedule GMP Update #7

ELM & STATE RESIDENTIAL

EXHIBIT C Construction Schedule

MJL

DE

Start milestone point Finish milestone point