LCI Preconstruction & Estimating Training Manual

Activity ID

Orig Dur

Early Start

Early Finish

2013

2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015

Description

OCT

NOV

DEC

WEATHER DELAY #9 - (Freezing Rain

042455 WEATHER DELAY #9 - (Freezing Rain)

0

03MAR15 A

WEATHER DELAY #10 - (High Wind)

052510 WEATHER DELAY #10 - (High Wind)

0

17MAR15 A

Completion of Underground Work

052450 Completion of Underground Work

0

28MAR15 A

SBC / Comcast

042450 SBC / Comcast

0

26MAY15

Install Slab-On-Grade Electrical

052442 Install Slab-On-Grade Electrical

10 27MAY15 09JUN15

Concrete Slab on Grade-Part 1

052445 Concrete Slab on Grade-Part 1

5 03JUN15

09JUN15

Concrete Slab on Grade-Part 2

052470 Concrete Slab on Grade-Part 2

5 09JUN15

15JUN15

Com Ed Vault Complete (Dried In)

042465 Com Ed Vault Complete (Dried In)

0 14JUL15

Establish COM-ED Permanent Power

042445 Establish COM-ED Permanent Power

0

21SEP15

STRUCTURAL CONCRETE ERECTION

Vertical 1 to 2 (Core and Columns)

070110 Vertical 1 to 2 (Core and Columns)

9 18MAR15 A 04APR15 A

WEATHER DELAY #11 - (Snow)

070220 WEATHER DELAY #11 - (Snow)

0

23MAR15 A

Level 2

070210 Level 2

8 08APR15 A 14APR15

Level 3

070340 Level 3

7 15APR15

23APR15

Level 4

070440 Level 4

6 23APR15 A 01MAY15

Level 5

070540 Level 5

20 29APR15 A 26MAY15

Reshores Removed 100% @ Level 1

070120 Reshores Removed 100% @ Level 1

0

26MAY15

Level 6

070640 Level 6

6 27MAY15 03JUN15

Reshores Removed 100% @ Level 2

070280 Reshores Removed 100% @ Level 2

0

03JUN15

Level 7

070740 Level 7

5 04JUN15

10JUN15

Reshores Removed 100% @ Level 3

070370 Reshores Removed 100% @ Level 3

0

10JUN15

Level 8

070840 Level 8

4 11JUN15

16JUN15

Reshores Removed 100% @ Level 4

070470 Reshores Removed 100% @ Level 4

0

16JUN15

Level 9

070940 Level 9

4 17JUN15

22JUN15

Reshores Removed 100% @ Level 5

070570 Reshores Removed 100% @ Level 5

0

22JUN15

Date

Revision

Checked Approved RAV PCC RAV PCC RAV PCC

Early bar Progress bar Critical bar Summary bar

31JAN15 23FEB15 28FEB15 08APR15

GMP Schedule GMP Schedule GMP Schedule GMP Update #7

ELM & STATE RESIDENTIAL

EXHIBIT C Construction Schedule