Level 8 - MEP/Framing

100820 Level 8 - MEP/Framing

35 23JUL15

09SEP15

Level 9 - MEP/Framing

100920 Level 9 - MEP/Framing

35 30JUL15

16SEP15

Level 10 - MEP/Framing

101020 Level 10 - MEP/Framing

35 06AUG15 23SEP15

Level 11 - MEP/Framing

101120 Level 11 - MEP/Framing

35 13AUG15 30SEP15

Level 12 - MEP/Framing

101220 Level 12 - MEP/Framing

35 20AUG15 07OCT15

Level 13 - MEP/Framing

101320 Level 13 - MEP/Framing

35 27AUG15 14OCT15

Level 14 - MEP/Framing

101420 Level 14 - MEP/Framing

35 03SEP15

21OCT15

Level 15 - MEP/Framing

101520 Level 15 - MEP/Framing

35 10SEP15

28OCT15

Level 16 - MEP/Framing

101620 Level 16 - MEP/Framing

35 17SEP15

04NOV15

Level 17 - MEP/Framing

101720 Level 17 - MEP/Framing

35 24SEP15

11NOV15

Level 18 - MEP/Framing

101820 Level 18 - MEP/Framing

35 01OCT15

18NOV15

Level 19 - MEP/Framing

101920 Level 19 - MEP/Framing

35 08OCT15

25NOV15

Level 20 - MEP/Framing

102020 Level 20 - MEP/Framing

35 15OCT15

02DEC15

Level 21 - MEP/Framing

102120 Level 21 - MEP/Framing

35 22OCT15

09DEC15

Level 22 - MEP/Framing

102220 Level 22 - MEP/Framing

35 29OCT15

16DEC15

Level 23 - MEP/Framing

102320 Level 23 - MEP/Framing

35 05NOV15 23DEC15

Level 24 - MEP

102420 Level 24 - MEP

25 12NOV15 16DEC15

DRYWALL/TAPING 100530 Level 5 - Drywall/Tape

Level 5 - Drywall/Tape

15 20AUG15 09SEP15

Level 6 - Drywall/Tape

100630 Level 6 - Drywall/Tape

15 27AUG15 16SEP15

Level 7 - Drywall/Tape

100730 Level 7 - Drywall/Tape

15 03SEP15

23SEP15

Level 5 - Whitebox Complete

100540 Level 5 - Whitebox Complete

0

09SEP15

Level 8 - Drywall/Tape

100830 Level 8 - Drywall/Tape

15 10SEP15

30SEP15

Level 6 - Whitebox Complete

100640 Level 6 - Whitebox Complete

0

16SEP15

Level 9 - Drywall/Tape

100930 Level 9 - Drywall/Tape

15 17SEP15

07OCT15

Level 7 - Whitebox Complete

100740 Level 7 - Whitebox Complete

0

23SEP15

Date

Revision

Checked Approved RAV PCC RAV PCC RAV PCC

Early bar Progress bar Critical bar Summary bar

31JAN15 23FEB15 28FEB15 08APR15

GMP Schedule GMP Schedule GMP Schedule GMP Update #7

ELM & STATE RESIDENTIAL

EXHIBIT C Construction Schedule

MJL

DE