Activity ID
Orig Dur
Early Start
Early Finish
2013
2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015
Description
OCT
NOV
DEC
Level 8 - MEP/Framing
100820 Level 8 - MEP/Framing
35 23JUL15
09SEP15
Level 9 - MEP/Framing
100920 Level 9 - MEP/Framing
35 30JUL15
16SEP15
Level 10 - MEP/Framing
101020 Level 10 - MEP/Framing
35 06AUG15 23SEP15
Level 11 - MEP/Framing
101120 Level 11 - MEP/Framing
35 13AUG15 30SEP15
Level 12 - MEP/Framing
101220 Level 12 - MEP/Framing
35 20AUG15 07OCT15
Level 13 - MEP/Framing
101320 Level 13 - MEP/Framing
35 27AUG15 14OCT15
Level 14 - MEP/Framing
101420 Level 14 - MEP/Framing
35 03SEP15
21OCT15
Level 15 - MEP/Framing
101520 Level 15 - MEP/Framing
35 10SEP15
28OCT15
Level 16 - MEP/Framing
101620 Level 16 - MEP/Framing
35 17SEP15
04NOV15
Level 17 - MEP/Framing
101720 Level 17 - MEP/Framing
35 24SEP15
11NOV15
Level 18 - MEP/Framing
101820 Level 18 - MEP/Framing
35 01OCT15
18NOV15
Level 19 - MEP/Framing
101920 Level 19 - MEP/Framing
35 08OCT15
25NOV15
Level 20 - MEP/Framing
102020 Level 20 - MEP/Framing
35 15OCT15
02DEC15
Level 21 - MEP/Framing
102120 Level 21 - MEP/Framing
35 22OCT15
09DEC15
Level 22 - MEP/Framing
102220 Level 22 - MEP/Framing
35 29OCT15
16DEC15
Level 23 - MEP/Framing
102320 Level 23 - MEP/Framing
35 05NOV15 23DEC15
Level 24 - MEP
102420 Level 24 - MEP
25 12NOV15 16DEC15
DRYWALL/TAPING 100530 Level 5 - Drywall/Tape
Level 5 - Drywall/Tape
15 20AUG15 09SEP15
Level 6 - Drywall/Tape
100630 Level 6 - Drywall/Tape
15 27AUG15 16SEP15
Level 7 - Drywall/Tape
100730 Level 7 - Drywall/Tape
15 03SEP15
23SEP15
Level 5 - Whitebox Complete
100540 Level 5 - Whitebox Complete
0
09SEP15
Level 8 - Drywall/Tape
100830 Level 8 - Drywall/Tape
15 10SEP15
30SEP15
Level 6 - Whitebox Complete
100640 Level 6 - Whitebox Complete
0
16SEP15
Level 9 - Drywall/Tape
100930 Level 9 - Drywall/Tape
15 17SEP15
07OCT15
Level 7 - Whitebox Complete
100740 Level 7 - Whitebox Complete
0
23SEP15
Date
Revision
Checked Approved RAV PCC RAV PCC RAV PCC
Early bar Progress bar Critical bar Summary bar
31JAN15 23FEB15 28FEB15 08APR15
GMP Schedule GMP Schedule GMP Schedule GMP Update #7
ELM & STATE RESIDENTIAL
EXHIBIT C Construction Schedule
MJL
DE
Start milestone point Finish milestone point
Return to Table of Contents
Made with FlippingBook flipbook maker