Level 10 - Drywall/Tap

101030 Level 10 - Drywall/Tape

15 24SEP15

14OCT15

Level 8 - Whitebox Complete

100840 Level 8 - Whitebox Complete

0

30SEP15

Level 11 - Drywall/Tape

101130 Level 11 - Drywall/Tape

15 01OCT15

21OCT15

Level 9 - Whitebox Complete

100940 Level 9 - Whitebox Complete

0

07OCT15

Level 12 - Drywall/Tape

101230 Level 12 - Drywall/Tape

15 08OCT15

28OCT15

Level 10 - Whitebox Complete

101040 Level 10 - Whitebox Complete

0

14OCT15

Level 13 - Drywall/Tape

101330 Level 13 - Drywall/Tape

15 15OCT15

04NOV15

Level 11 - Whitebox Complete

101140 Level 11 - Whitebox Complete

0

21OCT15

Level 14 - Drywall/Tape

101430 Level 14 - Drywall/Tape

15 22OCT15

11NOV15

Level 12 - Whitebox Complete

101240 Level 12 - Whitebox Complete

0

28OCT15

Level 15 - Drywall/Tape

101530 Level 15 - Drywall/Tape

15 29OCT15

18NOV15

Level 13 - Whitebox Complete

101340 Level 13 - Whitebox Complete

0

04NOV15

Level 16 - Drywall/Tape

101630 Level 16 - Drywall/Tape

15 05NOV15 25NOV15

Level 14 - Whitebox Complete

101440 Level 14 - Whitebox Complete

0

11NOV15

Level 17 - Drywall/Tape

101730 Level 17 - Drywall/Tape

15 12NOV15 02DEC15

Level 15 - Whitebox Complete

101540 Level 15 - Whitebox Complete

0

18NOV15

Level 18 - Drywall/Tape

101830 Level 18 - Drywall/Tape

15 19NOV15 09DEC15

Level 16 - Whitebox Complete

101640 Level 16 - Whitebox Complete

0

25NOV15

Level 19 - Drywall/Tape

101930 Level 19 - Drywall/Tape

15 26NOV15 16DEC15

Level 20 - Drywall/Tape

102030 Level 20 - Drywall/Tape

15 01DEC15

21DEC15

Level 17 - Whitebox Complete

101740 Level 17 - Whitebox Complete

0

02DEC15

Level 21 - Drywall/Tape

102130 Level 21 - Drywall/Tape

15 04DEC15

24DEC15

Level 22 - Drywall/Tape

102230 Level 22 - Drywall/Tape

15 08DEC15

29DEC15

Level 18 - Whitebox Complete

101840 Level 18 - Whitebox Complete

0

09DEC15

Level 23 - Drywall/Tape

102330 Level 23 - Drywall/Tape

15 10DEC15

31DEC15

Level 19 - Whitebox Complete

101940 Level 19 - Whitebox Complete

0

16DEC15

Date

Revision

Checked Approved RAV PCC RAV PCC RAV PCC

Early bar Progress bar Critical bar Summary bar

31JAN15 23FEB15 28FEB15 08APR15

GMP Schedule GMP Schedule GMP Schedule GMP Update #7

ELM & STATE RESIDENTIAL

EXHIBIT C Construction Schedule

MJL

DE

Start milestone point Finish milestone point

Return to Table of Contents

Made with FlippingBook flipbook maker