Activity ID
Orig Dur
Early Start
Early Finish
2013
2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015
Description
OCT
NOV
DEC
Level 24 - Drywall/Tap
102430 Level 24 - Drywall/Tape
5 17DEC15
23DEC15
Level 20 - Whitebox Complete
102040 Level 20 - Whitebox Complete
0
21DEC15
Level 24 - Whitebox Complete
102440 Level 24 - Whitebox Complete
0
23DEC15
Level 21 - Whitebox Complete
102140 Level 21 - Whitebox Complete
0
24DEC15
Level 22 - Whitebox Complete
102240 Level 22 - Whitebox Complete
0
29DEC15
Level 23 - Whitebox Complete
102340 Level 23 - Whitebox Complete
0
31DEC15
FINISHES 100120 Lobby Finishout
Lobby Finishout
130 23JUN15
21DEC15
Garage Core & Finishout
100420 Garage Core & Finishout
130 23JUN15
21DEC15
Level 5 - Finishes
100550 Level 5 - Finishes
65 10SEP15
09DEC15
Level 6 - Finishes
100650 Level 6 - Finishes
65 17SEP15
16DEC15
Level 7 - Finishes
100750 Level 7 - Finishes
65 24SEP15
23DEC15
Level 8 - Finishes
100850 Level 8 - Finishes
65 01OCT15
31DEC15
Level 9 - Finishes
100950 Level 9 - Finishes
65 08OCT15
08JAN16
Level 10 - Finishes
101050 Level 10 - Finishes
65 15OCT15
15JAN16
Level 11 - Finishes
101150 Level 11 - Finishes
65 22OCT15
22JAN16
Level 12 - Finishes
101250 Level 12 - Finishes
65 29OCT15
29JAN16
Level 13 - Finishes
101350 Level 13 - Finishes
65 05NOV15 05FEB16
Level 14 - Finishes
101450 Level 14 - Finishes
65 12NOV15 12FEB16
Level 15 - Finishes
101550 Level 15 - Finishes
65 19NOV15 19FEB16
Level 16 - Finishes
101650 Level 16 - Finishes
65 26NOV15 26FEB16
Level 17 - Finishes
101750 Level 17 - Finishes
65 03DEC15
04MAR16
Level 18 - Finishes
101850 Level 18 - Finishes
65 10DEC15
11MAR16
Level 19 - Finishes
101950 Level 19 - Finishes
65 17DEC15
18MAR16
Level 20 - Finishe
102050 Level 20 - Finishes
65 22DEC15
23MAR16
Level 21 - Finish
102150 Level 21 - Finishes
65 28DEC15
28MAR16
Date
Revision
Checked Approved RAV PCC RAV PCC RAV PCC
Early bar Progress bar Critical bar Summary bar
31JAN15 23FEB15 28FEB15 08APR15
GMP Schedule GMP Schedule GMP Schedule GMP Update #7
ELM & STATE RESIDENTIAL
EXHIBIT C Construction Schedule
MJL
DE
Start milestone point Finish milestone point