Activity ID
Orig Dur
Early Start
Early Finish
2013
2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015
Description
OCT
NOV
DEC
Level 22 - Finish
102250 Level 22 - Finishes
65 30DEC15
30MAR16
Level 23 - Finishes
102350 Level 23 - Finishes
65 04JAN16
18MAR16
Level 24 - Mechan
102450 Level 24 - Mechanical Penthouse Construction
50 07JAN16
16MAR16
ROOF/PENTHOUSE
Install Hoist Beams for Elevators
092025 Install Hoist Beams for Elevators
2 28SEP15
29SEP15
Install Divider Beams
092015 Install Divider Beams
5 30SEP15
06OCT15
Hoist HVAC Penthouse Equipment & Material
092005 Hoist HVAC Penthouse Equipment & Material
5 06OCT15
12OCT15
Hoist Plumbing Equipment
092006 Hoist Plumbing Equipment
5 06OCT15
12OCT15
Hoist Electrical Equipment
092007 Hoist Electrical Equipment
5 06OCT15
12OCT15
Install Stairs
092010 Install Stairs
2 06OCT15
07OCT15
Install Roof Blocking
092035 Install Roof Blocking
3 06OCT15
08OCT15
Install Elev Room/Penthouse Roof
092040 Install Elev Room/Penthouse Roof
5 09OCT15
15OCT15
Install Electrical Equipment @ Penthouse
092050 Install Electrical Equipment @ Penthouse
20 13OCT15
09NOV15
Install HVAC Equipment/Controls at Roof
092055 Install HVAC Equipment/Controls at Roof
35 13OCT15
30NOV15
Tie-In Roof Drains & other Plumbing Work
092060 Tie-In Roof Drains & other Plumbing Work
10 13OCT15
26OCT15
Install Roofing at Main Roof
092045 Install Roofing at Main Roof
5 16OCT15
22OCT15
Install Sheet Metal (Gutter/Downspouts/Flashin
092065 Install Sheet Metal (Gutter/Downspouts/Flashings
5 23OCT15
29OCT15
Plumbing Testing
092061 Plumbing Testing
2 27OCT15
28OCT15
Plumbing Fire Stopping
092062 Plumbing Fire Stopping
2 29OCT15
30OCT15
Plumbing Insulation
092063 Plumbing Insulation
2 29OCT15
30OCT15
Tower Watertight (Except at Hoist)
092070 Tower Watertight (Except at Hoist)
0
29OCT15
Plumbing Equip Identification & Marking
092081 Plumbing Equip Identification & Marking
2 02NOV15 03NOV15
Fire Protection Equip Identifiaction & Marking
092083 Fire Protection Equip Identifiaction & Marking
2 02NOV15 03NOV15
Electrical Fire Stopping
092053 Electrical Fire Stopping
2 10NOV15 11NOV15
Electrical Equip Identification & Marking
092082 Electrical Equip Identification & Marking
2 12NOV15 13NOV15
Date
Revision
Checked Approved RAV PCC RAV PCC RAV PCC
Early bar Progress bar Critical bar Summary bar
31JAN15 23FEB15 28FEB15 08APR15
GMP Schedule GMP Schedule GMP Schedule GMP Update #7
ELM & STATE RESIDENTIAL
EXHIBIT C Construction Schedule
MJL
DE
Start milestone point Finish milestone point