Activity ID
Orig Dur
Early Start
Early Finish
2013
2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015
Description
OCT
NOV
DEC
HVAC Fire Stopping
092056 HVAC Fire Stopping
2 17NOV15 18NOV15
HVAC Insulation (Ductwork/Pipe)
092057 HVAC Insulation (Ductwork/Pipe)
10 17NOV15 30NOV15
HVAC Equip Identification & Marking
092080 HVAC Equip Identification & Marking
2 01DEC15
02DEC15
Clean & Flush HVAC System
092085 Clean & Flush HVAC System
5 01DEC15
07DEC15
Fill HVAC System
092090 Fill HVAC System
2 08DEC15
09DEC15
ELEVATOR
Set Motor & Frames
092105 Set Motor & Frames
6 09OCT15
16OCT15
Drop Lines
092110 Drop Lines
5 19OCT15
23OCT15
Set Rails
092115 Set Rails
15 26OCT15
13NOV15
Set Pit Equipment
092120 Set Pit Equipment
5 16NOV15 20NOV15
Build Platform
092125 Build Platform
10 23NOV15 04DEC15
Set Sills & Frames
092130 Set Sills & Frames
10 07DEC15
18DEC15
Build Cab
092135 Build Cab
10 21DEC15
05JAN16
Complete Machine Room
092140 Complete Machine Room
5 06JAN16
12JAN16
Testing & Adjusting
092145 Testing & Adjusting
5 13JAN16
19JAN16
Comp. of Service Elevator for
092150 Comp. of Service Elevator for Const Hoisting
0
18JAN16
Passenger Elevator Finishes
092155 Passenger Elevator Finishes
5 19JAN16
25JAN16
Service Elevator Finishes
092165 Service Elevator Finishes
5 19JAN16
25JAN16
Completion of Passenger El
092160 Completion of Passenger Elevator
0
25JAN16
Completion of Service Eleva
092170 Completion of Service Elevator
0
25JAN16
MISCELLENEOUS
Install Material Hoist - Land Floors 2-8
092803 Install Material Hoist - Land Floors 2-8
2 25JUN15
26JUN15
Material Hoist Jump#1 - Land Floors 9-12
092806 Material Hoist Jump#1 - Land Floors 9-12
2 21JUL15
22JUL15
Material Hoist Jump#1-A - Land Floors 13-18
092816 Material Hoist Jump#1-A - Land Floors 13-18
2 24AUG15 25AUG15
Material Hoist Jump#2 - Land Floors 19-Roof
092809 Material Hoist Jump#2 - Land Floors 19-Roof
2 30SEP15
01OCT15
Date
Revision
Checked Approved RAV PCC RAV PCC RAV PCC
Early bar Progress bar Critical bar Summary bar
31JAN15 23FEB15 28FEB15 08APR15
GMP Schedule GMP Schedule GMP Schedule GMP Update #7
ELM & STATE RESIDENTIAL
EXHIBIT C Construction Schedule
MJL
DE
Start milestone point Finish milestone point
Return to Table of Contents