Activity ID
Orig Dur
Early Start
Early Finish
2013
2014 2016 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY UN 2015
Description
OCT
NOV
DEC
Dismantle Hoist
092818 Dismantle Hoist
3 22DEC15
24DEC15
Complete Enclosure at Hoist L
092821 Complete Enclosure at Hoist Location (All Floors
15 28DEC15
18JAN16
Exterior Painting
092830 Exterior Painting
20 31DEC15
28JAN16
PROJECT CLOSEOUT
Turnover First Units
113215 Turnover First Units
0
28JAN16
Weather Days
113245 Weather Days
9 21MAR16 31MAR16
Turn Over Las
113225 Turn Over Last Units
0
31MAR16
Leopardo Co's
113235 Leopardo Co's Substantial Completion
0
01APR16
UNIT TURNOVER
Turnover - Floors 5,6,7,8
113255 Turnover - Floors 5,6,7,8
0
28JAN16
Turnover - Floors 9,10,
113265 Turnover - Floors 9,10,11,12
0
18FEB16
Turnover - Floors 1
113275 Turnover - Floors 13,14,15
0
10MAR16
Turnover - Floo
113285 Turnover - Floors 16,17,18
0
31MAR16
Turnover - Floo
113305 Turnover - Floors 22, 23
0
31MAR16
Turnover -
113295 Turnover - Floors 19, 20, 21
0
21APR16
Date
Revision
Checked Approved RAV PCC RAV PCC RAV PCC
Early bar Progress bar Critical bar Summary bar
31JAN15 23FEB15 28FEB15 08APR15
GMP Schedule GMP Schedule GMP Schedule GMP Update #7
ELM & STATE RESIDENTIAL
EXHIBIT C Construction Schedule
MJL
DE
Start milestone point Finish milestone point