LCI Preconstruction & Estimating Training Manual

61 East Bank Street

7/15/2016

$

38,054,169 40,998,076

RFP Estimate Dated 2/22/16

$

DesignDevelopment Estimate Dated 7/15/16

$

2,943,907

Estimate Savings/Overrun

Scope Adjustments (Increases/Decreases)from the Revised Initial Estimate

72 73 74 75 76 77 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99

New dtl: Entry overhang framing (dtl#1/A502) - 68 lf Adjustment to roof steel assumptions

$ $

7,039.00 8,500.00

$

334,160.00

Add 1 residential unit @ $6,000/unit cabinet allowance Div 6 - Woods and Plastics Eliminate wall panels in club room Add PLAM cabinets and solid surface top in 1st floor kitchen

$ $ $

(10,968)

2,145 6,000

Rooftop pergola - at rooftop: (simplified, reduce horizontal members;Rooftop pergola - at rooftop: (added SF);IPE wood decking - at rooftop;IPE wood screenwall, per A201, 9' H: Added scope;Trellis fence at south patio, 5' high (112 lf) per L100C: Added scope;Pricing adjustments made to accommodate 1)crew rate productions achieved, 2) design simplicity

$

(20,582.00)

$

(23,405.00)

Div 7 - Waterproofing/Vapor Barrier

Air barrier on exterior perimeter walls unit cost market adjustment/increase by $2.86/SF [$3.5/SF(RFP) vs. $6.26/SF (DD)] Waterproofing on basement walls Quantity Increase of 3,758SF @ $6.70/SF [5,120SF (RFP) vs. 8,878SF (DD)] Waterproofing unit cost market adjustment/increase by $3.3/SF [$3.4/SF in RFP to $6.7/Sf in DD]

$ $ $

25,179 16,896 42,378

$

84,452.60

Div 7 - Metal Panel

Eliminate Metal Panel at Mech. Screen Wall - This scope is now IPE Wood siding panel included in "06660 Wood Pergola and Rooftop Decking"

$ $

(22,150) (48,755)

Eliminate Metal Panel siding at Penthouse Walls - This scope is now shown as EIFS on DD set drawings

$

(70,905.00)

Div 7 - Spray Insulation

Provide Spray insulation at Metal Stud & Drywall

$ $

140,000 100,000

Spray insulation garage ceiling

$

240,000.00

Div 7 - Roofing

Added Vector Field Mapping per DD Drawing

$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $

5,858 6,750

Market Adjustment - Membrane Roofing Added Flashing for added window washing davit anchors to meet the code (based on Probel's preliminary engineering) Market Adjustment - Waterproofing over parking deck, outside building footprint, lev00

40,096 12,684 51,370

100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144

Added Prefinished Sheet Metal Roofing at top of Bay window area (detail 1/A500)

$

116,758.00

Div 8 - Openings

Additional Window Wall Quantity (slab edge and window wall) - "750 SF" increase [25,425SF(DD) vs. 24,675SF(RFP)] Premium for the Ellison SS clad aluminum door at main entry

67,000

7,000

100,050 312,652

Market Adjustment - Punched Window Area (No quantity Change) Market Adjustment - Window Wall/Bay window area (Incl. Slab Edge Detail)

Additional 11LF of Railing

4,565

Market Adjustment - Glass Railing

10,710

1,600

Market adjustment for exercise room mirrors Eliminate main lobby glazing; none shown on drawings

(2,889) (18,820)

Market adjustment for doors/frames/hardware; added quantity Reduction in quantity of bathroom mirrors; market unit cost adjustment

73,933

$

555,801

Div 9 - Finishes

Scope Change - Provide EIFS at Penthouse ILO previously assumed metal panel at penthouse ($25/SF) - See above credit in Metal Panel

73,895

Minor adjustment of painting quantities in core & shell Reduce carpet corridor by 506 SY Minor reduction of fitness room flooring quantity Reduce wood flooring quantity by 4,256 SF Reduce wood base and shoe quantity by 1,257 LF Reduction in residential quantity of painting Reduce vinyl base by 2934 LF Added floor tile in elevator lobbies; floor tile at unit entrances

(38,302) (2,263) (58,237) (9,752) (16,181) (1,540) (7,337) 44,499 (17,386) 135,209

Reduce residential bedroom carpet by 580 SY

Steel material escalation; labor escalation for metal stud and drywall; changes to demising walls

Add/deduct in tile quantities in residential units

9,673

Misc.

13,946

$

126,224

Div 10 - Specialties Reduce allowances for powder room, master bathroom and guest bathroom toilet accessory packages

(28,200)

Minor market adjustment for FEC and FE material costs

1,130 2,550

Addtiional 22 glass shower doors Add 1 additional mailbox and minor market adjustment for material cost Reduction in quantity of MDF shelf and rod at residential unit closets

55,000

(56,423)

$

(25,943)

-

Revised Budget Based on Code Compliant Engineering Div 11 - Equipment Market adjustment for trash chutes (received two proposals)

3,533

(49,826) (23,912)

Reduce appliance allowance from $15,000/unit to $14,280/unit; added 1 additional unit

$

(70,205)

Division 13 - Glass Canopy

Addtl. "249SF" of Glass Canopy [526SF(DD) vs. 277SF (RFP)]

$

21,277

$

21,277.00

Div 14 - Conveying Systems

Page 2 of 3 Return to Table of Contents