LCI Preconstruction & Estimating Training Manual

BIDDING / APPROVAL PROCESS SUN ISLAND HOTEL, RESORT AND CONFERENCE FACILITY HOFFMAN ESTATES, ILLINOIS

100% CD Drawings Due from architect Or Bid Package Drawings

Leopardo Constructability Review/Develop Scopes

Architect Incorporates

Leopardo Finalizes Bid Scopes/Documents

Revisions – issues final corrected bid documents

2 days

Leopardo Review and Issues Addendum to Subcontractors

Architect Issues Addendum to Leopardo

Pre-Bid Meeting

Cut-off for Bidder Questions

Out to Bid

3 days

TOTAL PROCESS FROM START TO FINISH:

33

Work Days

Bids Due

Post Bid Review

6.6 Weeks 1.52 Months

Return to Table of Contents