BIDDING / APPROVAL PROCESS SUN ISLAND HOTEL, RESORT AND CONFERENCE FACILITY HOFFMAN ESTATES, ILLINOIS
100% CD Drawings Due from architect Or Bid Package Drawings
Leopardo Constructability Review/Develop Scopes
Architect Incorporates
Leopardo Finalizes Bid Scopes/Documents
Revisions – issues final corrected bid documents
2 days
Leopardo Review and Issues Addendum to Subcontractors
Architect Issues Addendum to Leopardo
Pre-Bid Meeting
Cut-off for Bidder Questions
Out to Bid
3 days
TOTAL PROCESS FROM START TO FINISH:
33
Work Days
Bids Due
Post Bid Review
6.6 Weeks 1.52 Months