Project Schedule – Milestone Activities
MILESTONE ACTIVITY
SCHEDULED START
SCHEDULED COMPLETION
1. Garage Elevator
May 5, 2008
June 30, 2008
2. Structural Ex. Begins
March 26, 2008
April 3, 2008
3. Anchor Bolts and Embeds onSite 4. Cast-in-place Foundations Pour
April 2, 2008
N/A
April 10, 2008
May 13, 2008
5. 2nd Floor East Deck Pour
June 11, 2008
June 13, 2008
6. 2nd Floor Center Deck Pour June 20, 2008
June 24, 2008
7. 2nd Floor West Deck Pour
June 26, 2008
June 30, 2008
8. 3rd Floor East Deck Pour
July 11, 2008
July 15, 2008
9. 3rd Floor West Deck Pour
July 17, 2008
July 21, 2008
10. PHQ Elevators
August 20, 2008 December 23, 2008
(Detailed schedule can be found in Section 003113 of the Project Manual)