LCI Preconstruction & Estimating Training Manual

Project Schedule – Milestone Activities

MILESTONE ACTIVITY

SCHEDULED START

SCHEDULED COMPLETION

1. Garage Elevator

May 5, 2008

June 30, 2008

2. Structural Ex. Begins

March 26, 2008

April 3, 2008

3. Anchor Bolts and Embeds onSite 4. Cast-in-place Foundations Pour

April 2, 2008

N/A

April 10, 2008

May 13, 2008

5. 2nd Floor East Deck Pour

June 11, 2008

June 13, 2008

6. 2nd Floor Center Deck Pour June 20, 2008

June 24, 2008

7. 2nd Floor West Deck Pour

June 26, 2008

June 30, 2008

8. 3rd Floor East Deck Pour

July 11, 2008

July 15, 2008

9. 3rd Floor West Deck Pour

July 17, 2008

July 21, 2008

10. PHQ Elevators

August 20, 2008 December 23, 2008

(Detailed schedule can be found in Section 003113 of the Project Manual)

Return to Table of Contents

Made with FlippingBook flipbook maker