SECTION 00220 WORK SCOPE
SECTION 00220 WORK SCOPE
BID CATEGORY 06100 - Carpentry
BID CATEGORY 09650 - Flooring
The Work of this Bid Category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Carpentry in accordance with the Contract Documents and applicable codes. All Work is to be performed as shown on the plans and specified in the following technical Specification sections:
The Work of this Bid Category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all Flooring in accordance with the Contract Documents and applicable codes. All Work is to be performed as shown on the plans and specified in the following technical Specification sections:
Section
Name
Section
Name
In addition to the above, this Bid Category requires adherence to and coordination with various other technical Specifications interfacing with this Work. The Bidder shall review the Work descriptions of the other Bid Categories as set forth in Section 00210 of the Project Manual [INSERT IF REQUIRED - and other referenced documents] so as to not misunderstand scope responsibilities.
In addition to the above, this Bid Category requires adherence to and coordination with various other technical Specifications interfacing with this Work. The Bidder shall review the Work descriptions of the other Bid Categories as set forth in Section 00210 of the Project Manual [INSERT IF REQUIRED - and other referenced documents] so as to not misunderstand scope responsibilities.
THE SCOPE OF WORK IS TO INCLUDE, but is not limited to, the following items:
THE SCOPE OF WORK IS TO INCLUDE, but is not limited to, the following items:
[INSERT DESCRIPTIONS OF WORK SCOPE AND NUMBER ITEMS AS REQUIRED WITH MOST IMPORTANT/BROADEST ITEMS FIRST]
[INSERT DESCRIPTIONS OF WORK SCOPE AND NUMBER ITEMS AS REQUIRED WITH MOST IMPORTANT/BROADEST ITEMS FIRST]
1.
1.
EXCLUDED FROM THIS CONTRACTOR'S WORK is:
EXCLUDED FROM THIS CONTRACTOR'S WORK is:
[INSERT WORK EXCLUSIONS AND NUMBER ITEMS AS REQUIRED] 1.
[INSERT WORK EXCLUSIONS AND NUMBER ITEMS AS REQUIRED] 1.
SPECIAL CONSIDERATIONS [VERIFY THAT THE FOLLOWING APPLIES TO THIS PROJECT]:
SPECIAL CONSIDERATIONS [VERIFY THAT THE FOLLOWING APPLIES TO THIS PROJECT]:
11. All work under this scope shall comply with proper trade jurisdictions, even if it is necessary to assemble composite crews or subcontract to appropriate trades . 12. Include costs to provide one laborer responsible for waste material handling of this contractor’s construction debris. Separate dumpsters will be provided for separation of waste and recyclable materials. 13. Mechanical and Electrical contractors shall assist with commissioning process to meet LEED requirements.
16. All work under this scope shall comply with proper trade jurisdictions, even if it is necessary to assemble composite crews or subcontract to appropriate trades . 17. Include costs to provide one laborer responsible for waste material handling of this contractor’s construction debris. Separate dumpsters will be provided for separation of waste and recyclable materials. 18. Mechanical and Electrical contractors shall assist with commissioning process to meet LEED requirements.
14. Special Consideration #1 15. Special Consideration #2
19. Special Consideration #1 20. Special Consideration #2
END OF SECTION 00220
END OF SECTION 00220
PROJECT MANUAL – REV DATE: 11/05 SECTION 00220 – Work Scope BID CATEGORY 06100 - Carpentry
00220-1
ISSUE DATE: January 1, 2006
PROJECT MANUAL – REV DATE: 11/05
00220-1
ISSUE DATE: January 1, 2006
SECTION 00220 – Work Scope BID CATEGORY 09650 - Flooring
Leopardo Companies Inc.
Acme Hospital
Leopardo Companies Inc.
Acme Hospital
SECTION 00220 WORK SCOPE
SECTION 00230 SCHEDULE AND PHASING
PART 1 - GENERAL
BID CATEGORY 001524 – CONSTRUCTION WASTE MANAGEMENT
The Work of this Bid Category includes but is not limited to providing all labor, equipment, materials, scaffolding, hoisting and incidentals to complete all 001524 – Construction Waste Management in accordance with the Contract Documents and applicable codes. All Work is to be performed as shown on the plans and specified in the following technical Specification sections:
1.01
RELATED DOCUMENTS
A. Attention is directed to Bidding and Contract Requirements, and to Division 1, General Requirements, which are hereby made a part of this Section.
Section
Name
1.02
MILESTONE SCHEDULE
A. The following are the milestone schedule dates for the listed Work and will become a part of the Contract Documents. The master construction schedule will be developed after award of the Agreement with Subcontractor input.
In addition to the above, this Bid Category requires adherence to and coordination with various other technical Specifications interfacing with this Work. The Bidder shall review the Work descriptions of the other Bid Categories as set forth in Section 00210 of the Project Manual [INSERT IF REQUIRED - and other referenced documents] so as to not misunderstand scope responsibilities.
MILESTONE ACTIVITY
SCHEDULED START
SCHEDULED COMPLETION
THE SCOPE OF WORK IS TO INCLUDE, but is not limited to, the following items:
[INSERT DESCRIPTIONS OF WORK SCOPE AND NUMBER ITEMS AS REQUIRED WITH MOST IMPORTANT/BROADEST ITEMS FIRST]
[INSERT DESCRIPTIONS AND DATES - CAUTION IS NOTED AS TO SPECIFICS OF MILESTONE DATES RELATIVE TO SEQUENCING]
1. Furnish, install, maintain, replace, relocation, and remove all required dumpsters on-site for use for contractor’s debris. 2. Provide separate dumpsters for separation of recyclable and waste materials. Include list of acceptable and unacceptable materials on proper signage at each container. 3. Implement a waste management plan for the project, including training for each trade. 4. Inspect containers and bins for contamination prior to removal from site. Should any contamination be present, immediately notify Leopardo Companies Inc. for correction of the contamination. Contractor shall not remove dumpster from site until contamination is corrected. 5. Attend weekly contractor meetings to provide updates on waste management and answer questions.
[PROVIDE BIDDERS WITH A GENERAL SEQUENCE OF CONSTRUCTION -IF DETAILED SEQUENCING AND NARRATIVES ARE REQUIRED, REFER TO PART 2 - PHASING]
[INSERT ONLY FOR RENOVATION PROJECTS - Close coordination will be required between all construction trades in order that individual areas of renovation and new construction can be completed within the scheduled time. Consult the proposed construction sequence and renovation sequence schedules and key plans found in, Part 2 for start and completion dates of individual Work areas.] B. It is expressly agreed that time is of the essence for the completion of Work under the Agreement and Subcontractor agrees to perform the Work within the allotted time and in the manner specified. Subcontractor shall be liable for any and all damages and expenses suffered by the Owner or Leopardo Companies Inc. arising or resulting from the failure of Subcontractor to perform the Work in accordance with the construction schedule.
EXCLUDED FROM THIS CONTRACTOR'S WORK is:
[INSERT WORK EXCLUSIONS AND NUMBER ITEMS AS REQUIRED] 1.
1.03
CONSTRUCTION SCHEDULE DEVELOPMENT PROCESS
A. Subcontractor agrees to commence Work in the field within five (5) Days after being notified to do so by the Leopardo Companies Inc.. Subcontractor shall diligently perform and fully complete all Work to the satisfaction of Leopardo Companies Inc. and Owner.
Work shall begin at such points as Leopardo Companies Inc. may designate and shall be carried to completion with the utmost speed.
B. Subcontractor shall submit to Leopardo Companies Inc. [INSERT - within fifteen (15) Days of award of the Agreement [INSERT a Bar Chart/CPM] construction schedule using the [INSERT SOFTWARE NAME] software OR all necessary scheduling information using Leopardo Companies Inc. specified coding] of all activities contained in the Subcontractor’s scope of Work. This schedule shall include activity descriptions and durations in working days, for shop drawings, fabrication, delivery and installation
ISSUE DATE: January 1, 2006 Return to Table of Contents
PROJECT MANUAL – REV DATE: 11/05
00220-1
SECTION 00220 – Work Scope BID CATEGORY 001524 – Construction Waste Management
PROJECT MANUAL – REV DATE: 1/04 SECTION 00230 – Schedule and Phasing
00230-1
ISSUE DATE: January 1, 2006