LCI Preconstruction & Estimating Training Manual

Subcontractor Bid Recap Report

Bid Due: 7/15/2016

LCI Project #: Project Name:

15-1389-DD 61 East Banks Development 61East Banks Chicago, IL

Estimator:

Eui, Chirs , Paul and Syed J. Sauline

Floor Area-S.F.:

151,057

Address:

Project Manager:

Start:

12/14/2016 10/25/2015

City, State:

Complete: Project Duration:

60

Weeks

BIDDER BIDDER BIDDER BIDDER BIDDER BIDDER 1 2 3 4 5 6

LCI ESTIMATE

BEST BID- QUALIFIED

BID USED- PROPOSAL

ITEM CODE & DESCRIPTION

$/SF

$/SF

Notes

DIVISION 9 - Finishes

PCI $3,984,524

$3,984,524

$26.38

$3,984,524

$3,984,524

$26.38

09252 Metal Stud & Drywall

$706,673

$706,673

$706,673

$4.68

$4.68

09310 Hard Tile

PCI $175,128 Skyline $88,050

$40,600

$40,600

$40,600

$0.27

$0.27

09510 Acoustical Ceilings

PCI

JP Phillips

11/10/15 $14,155

$91,025

$0.60

$88,050

$88,050

$0.58

09006 E.I.F.S./Synthetic Plaster

Declined Declined

$161,873

$161,873

$161,873

$1.07

$1.07

09685 Carpet & Resilient Flooring

$595,875

$3.94

$595,875

$595,875

$3.94

09900 Painting & Wallcovering

$151,270

$1.00

$151,270

$151,270

$1.00

09695 Floor Preparation - Misc.

$535,086

$535,086

$3.54

$535,086

$3.54

09560 Wood Flooring & Base

DIVISION 10 - Specialties

$0.16

$23,800

$23,800

$23,800

$0.16

10800 Toilet Accessories

$8,000

$0.05

$8,000

$8,000

$0.05

10523 Fire Extinguishers & Cabinets

$7,625

$0.05

$7,625

$7,625

$0.05

10550 Postal Specialties

$0.08

$12,580

$12,580

$0.08

$12,580

10430 Directional Signage/Graphics

$162,500 $1.08

$162,500

$162,500

$1.08

10186 Glazed shower door enclosures

$53,300

$53,300

$53,300 $0.35

$0.35

10916 Closet Shelving

DIVISION 11 - Equipment

Probel $39,675

Tractel

11/10/15 $89,501

$55,400

$0.37

$39,675

$39,675

$0.26

11013 Window Washing Systems

Antonelli &

American

$28,800

$0.19

$27,400

$27,400

$0.18

11175 Trash Chutes

$27,615

$27,400

$0.02

$3,500 $0.02

$3,500

$3,500

11164 Loading Dock Equipment

$871,080 $5.77

$871,080

$871,080

$5.77

11451 Residential Appliances

Alternate

Alternate

11452 Fireplaces

By owner

By owner

11176 Trash Compactor

DIVISION 12 - Furnishings

$116,328

$0.77

$116,328

$116,328

$0.77

12530 Window Treatment

$0.11

$17,000

$0.11

$17,000

$17,000

12480 Floor Mats & Frames

DIVISION 13 - Special Construction

N/A

N/A

13170 Tubs and Pools

ALLOWANCE Prime/LCI Northern/LCI $56,883 $81,730 $78,160

$78,360

$0.52

$0.52

$78,160

$78,160

13200 Entrance Canopy (Allowance)

Return to Table of Contents