LCI Preconstruction & Estimating Training Manual

Scope Recap Report

09252 Metal Stud & Drywall

.

16-2596 300 West Huron 300 West Huron Chicago, IL

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

1

2

3

4

5

6

Phone #

Company Name Contact Phone #

Company Name Contact Phone #

Company Name Contact Phone #

Phone #

Company Name Contact Phone #

Company Name Contact

Company Name Contact

ESTIMATE

ITEM BREAKDOWN

Qty.

Unit Price

Total

Area

INITIAL BID

addendums taxes P&P bond (price as alternate) bonding capacity - $____________ EMR rating __________ LEED-related requirements per specs scope

budget

Building Enclosure

E E

1st Floor Cold Formed Framing Partitions Exterior Enclosure - 1st Floor behind stone panels Metal Panel Cladding Cold Formed Framing

1,500 SF $25.15

$37,725 $31,980

E E

533

LF $60.00

Exterior Soffit Framing for metal panels; including densglass (Air barrier in div 7)

E E E E E E

4th Floor Soffit/Canopy Ceiling 10th Floor Terrace Ceilings 11th Floor Terrace Ceilings 17th Floor Terrace Ceilings 18th Floor Terrace Ceilings

6,427 SF $8.08 1,429 SF $8.08 4,484 SF $8.08 1,437 SF $8.08 4,204 SF $8.08

$51,898 $11,539 $36,208 $11,604 $33,947

Exterior Framing @ 25th Floor - Wall Type F1 North Exterior Wall Dividing Mechanical Space and Cooling Tower Enclosure

E

473 SF $25.15

$11,901

E E G G G G G G

Garage

2nd Floor Lobby

Drywall to deck with insulation

135 SF $6.41 171 SF $6.18

$866

Drywall Ceiling 3rd Floor Lobby

$1,056

Drywall to deck with insulation

210 SF $6.41

$1,347

Div 9 Return to Table of Contents