LCI Preconstruction & Estimating Training Manual

Scope Recap Report

09252 Metal Stud & Drywall

.

16-2596 300 West Huron 300 West Huron Chicago, IL

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

BIDDER

1

2

3

4

5

6

Phone #

Company Name Contact Phone #

Company Name Contact Phone #

Company Name Contact Phone #

Phone #

Company Name Contact Phone #

Company Name Contact

Company Name Contact

ESTIMATE

ITEM BREAKDOWN

Qty.

Unit Price

Total

Area

23rd Floor

1

FL

CS CS CS CS CS CS CS CS CS CS

Elevator Shaft Wall

218 SF $15.68

$3,423

Trash Chute Shaft Wall

55

SF $15.68

$856

Duct Shaft Wall

186 SF $15.68

$2,910

Electrical Room 1HR Rated

76

SF $8.79

$672

24th Floor

1

FL

Elevator Shaft Wall

247 SF $15.68

$3,865

Trash Chute Shaft Wall

62

SF $15.68

$966

Duct Shaft Wall

210 SF $15.68

$3,286

Electrical Room 1HR Rated

86

SF $8.79

$758

25th Floor

1

FL

CS CS

Stairwell Ceilings

332 SF $6.18

$2,050

Back of House

B B B B B B B B B B B B B B B B B B B B B

1st Floor

1HR rated wall 2HR rated wall 3HR rated wall

1,140 SF $8.79 2,016 SF $12.35 228 SF $16.15 5,052 SF $4.99

$10,018 $24,898 $3,682 $25,197

Furred Partitions @ Exterior CMU Walls

5th - 10th Floor

5

FL

1HR rated wall @ trash room

75

SF $8.79

$659

11th and 18th Floor

2

FL

1HR rated wall @ trash room

30

SF $8.79

$264

12th - 17th Floor

6

FL

1HR rated wall @ trash room

90

EA $8.79

$791

19th - 22nd Floor

4

FL

1HR rated wall @ trash room

60

EA $8.79

$527

23rd Floor

1

FL

1HR rated wall @ trash room

15

EA $8.79

$132

Div 9 Return to Table of Contents