CONTRACT CLOSEOUT
_
Section 0l700 - Page 0l700-3
l.7
WARRANTIES A.
Provide triplicate copies. Execute Contractor's submittals and assemble documents executed by
subcontractors, suppliers and manufacturers. Provide table of contents and assemble in binder with durable plastic cover. B. Submit material prior to final application for payment. For items of Work delayed materially beyond Date of Substantial Completion, provide updated submittal within ten days after acceptance, listing date of acceptance as start of warranty period.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION