Bid 1093 - Security Replacement Project at OCS - Invitation…

WARRANTIES

Section 0l740 - Page 0l740-2

l.4

FORM OF SUBMITTALS A.

Prepare in duplicate packets.

B.

Format: l.

Size 8-l/2" x ll", punch sheets for standard three-ring binder. a. Fold larger sheets to fit into binders. Cover: Identify each packet with types or printed title "Warranties". List: a. Title of Project b. Name of Contractor

2.

C. Binders: Commercial quality, three-ring, with durable and cleanable plastic covers.

l.5

TIME OF SUBMITTALS A. For equipment or component parts of equipment put in to service during progress of construction: l. Submit documents within l0 days after inspection and acceptance. B. Otherwise make submittals within l0 days after Date of Substantial Completion, prior to final request for payment. C. For items of work, where acceptance is delayed materially beyond Data of Substantial Completion, provide updated submittals within l0 days after acceptance, listing date of acceptance as start of warranty period.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION