Bid 1093 - Security Replacement Project at OCS - Invitation…

BASIC ELECTRICAL MATERIALS AND METHODS

Section 0l750 - Page 0l750-7

C. Material Selection: The Electrical Contractor shall review all drawings related to the project to assure proper materials are being installed for the environmental conditions of the space. Any questions shall be directed to the Engineer for clarification prior to the bid date.

PART 3 – EXECUTION

3.1 INSTALLATION

A. Location 1. Carefully investigate the structural and finish conditions affecting the work and arrange all work accordingly, furnishing necessary parts and equipment to meet the various conditions. 2. Coordinate the plan locations and mounting heights of equipment with the location of existing equipment.

B. Critical Circuits

C. Identification Nameplates

D. Coordination With Others This Contractor shall cooperate with the Owner in the scheduling of his work so that he does not delay or interfere with facility operations, and shall also check the location of his equipment with others to avoid space conflicts. E. Protection of Work This Contractor shall be held responsible for the protection of and damage to his work prior to the final acceptance of same, and shall repair or replace all damaged work at his own expense.

Made with FlippingBook Online newsletter maker