SECTION 0l100
Section 0l100 - Page 0l100-1
SUMMARY PART 1-GENERAL
1.1
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2
SUMMARY
A.
This Section includes the following: 1. Identification of the Project Owner, Engineer and the Contract Documents. 2. Work covered by the contractor. 3. Use of Premises. 4. Owners occupancy requirements. 5. Work Restrictions.
1.3
CONTRACTS
Without force or effect on the Contract Documents, the work may generally be described as follows:
1.4
SCHEDULE AND DELIVERY OF THE WORK
The Contractor will publish a schedule as part of the bidding documents, detailing the anticipated commencement date of the Work and required date of Substantial Completion. The Contractor(s) shall schedule and coordinate activities required by the Work to align with stated delivery dates.