ALTERATION PROJECT PROCEDURES
SECTION 0l03l
Section 0l03l - Page 0l03l-l
ALTERATION PROJECT PROCEDURES
PART l GENERAL
l.
0l REQUIREMENTS INCLUDED A.
The Prime Contractor will coordinate work of trades and schedule elements of alterations and renovation work by procedures and methods to expedite completion of the work. Patch, repair and refinish existing items to remain to the specified condition for each material with a workmanlike transition to adjacent new items of construction. No work on this project will jeopardize, reduce, eliminate or in any way effect existing warranties or guarantees now in place for this building or its building envelope or systems.
B.
C.
l.2
RELATED REQUIREMENTS A.
Section 0l0l0 - Summary of Project
B.
Section 0l045 - Cutting and Patching
Section 0l300 − Submittals
C. D.
Section 0l500 - Construction Facilities & Temporary Controls
Section 0l540 − Security Section 0l7l0 - Cleaning
E. F.
l.3
SEQUENCE AND SCHEDULES A.
Schedule work as specified in Section 0l0l0.
B.
Submit separate detailed subschedule for Alterations work, coordinated with the Construction Schedules. Show: l. Each stage of work, and dates of occupancy of areas. 2. Date of Substantial Completion for each area of alterations work, as appropriate. 3. Trades and subcontractors employed in each stage.