Bid 1093 - Security Replacement Project at OCS - Invitation…

CHANGE ORDER PROCEDURES

SECTION 0ll53

Section 0ll53 - Page 0ll53-l

CHANGE ORDER PROCEDURES

PART l GENERAL

l.

0l REQUIREMENTS INCLUDED A.

Promptly implement change order procedures. l. Provide full written data required to evaluate changes. 1. Maintain detailed records of any work authorized to be done on a time-and-material account basis.

2.

Provide full documentation for Owner on request.

B. Designate in writing the member(s) of Contractor's organization. l. Who is authorized to accept changes in the Work. 2. Who is responsible for informing others in the Contractor's employ of the authorization of changes in the work. C. Only the Director of the Owner's Facilities Management Division or his designated representative can authorize changes to Contract. D. Only fully documented, written change orders will be processed for payment. Any work performed without this approval process will be at the Contractor ’ s expense. Conditions of the Contract: l. Methods of determining cost or credit to Owner resulting from changes in Work. 2. Contractor's claims for additional costs. C. Section 0ll52 - Applications for Payment D. Section 0l300 - Submittals E. Section 0l600 - Materials and Equipment F. Section 0l700 - Contract Closeout RELATED REQUIREMENTS A.

l.2