SUBMITTALS

SECTION 0l300

Section 0l300 - Page 0l300-l

SUBMITTALS PART l GENERAL

l.

0l REQUIREMENTS INCLUDED A. Procedures B.

Construction Progress Schedules

C. D. E. F. G.

Schedule of Values

Shop Drawings

Product Data

Samples

Manufacturer's Certificates

l.2

RELATED REQUIREMENTS

A.

Section 0l0l0 - Summary of Project

B.

Section 0ll52 - Applications for Payment:

Submittal

of Applications

C.

Section 0l600 - Material and Equipment:

Manufacturers' Instructions Substitutions and Product Options: Contractor's List of Products D. Section 0l700 - Contract Closeout: Closeout Submittals

l.3

PROCEDURES A.

Deliver six (6) copies of submittals to Project Manager at address listed in Section 0ll52, paragraph l.03, A. B. Transmit each item under AIA Form 8l0. Identify Project, Contractor, subcontractor, major supplier; identify pertinent Drawing sheet and detail number, and Specification section number, as appropriate. Identify deviations from Contract Documents. Provide space for Owner/Engineer review stamps. C. Submit initial Project schedule, progress schedules, schedule of values, shop Drawings and product data as

required no later than l5 days after award of Contract. After review by College, revise and

resubmit as required. Submit revised schedules with each Application for Payment reflecting changes since previous submittal. D. Comply with progress schedule for submittals related to Work progress. Coordinate submittal of related items.