SUBMITTALS

Section 0l300 - Page 0l300-3

l.7

PRODUCT DATA A.

Mark each copy to identify applicable Products, models, options and other data; supplement manufacturers' standard data to provide information unique to the Work. Include manufacturers' installation instructions when required by the Specification section. B. Submit the number of copies which Contractor requires, plus three copies which will be retained by College.

l.8

MANUFACTURERS' CERTIFICATES A.

Submit certificates, in duplicate.

1.9

MBE & WBE UTILIZATION A.

Submit monthly MBE and WME reports for Contractor to the Project Manager. These are to be submitted with the Contracto r’s Request for Payment but no less than monthly.

B.

1.10

EEO A.

Submit monthly reports as required showing number of employees for Contractor and subcontractors to the Project Manager. B. These are to be submitted with the Contracto r’s request for payment but not less than monthly.

1.11

CERTIFIED PAYROLLS A.

Contractors, subcontractors and all lower tier subcontractors shall submit weekly certified payrolls to the Project Manager.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION Not Used

END OF SECTION