Community College of Allegheny County Pittsburgh, Pennsylvania
2022 Library Roofing Project
SECTION 02060 DEMOLITION
PART 1- GENERAL
1.01
RELATED DOCUMENTS
A. Drawings and Contract Documents, including Section 01010 Summary of Work , apply to work of this section.
1.02
SECTION INCLUDES
A. Existing conditions, demolition by removal and disposal of existing membrane to substrate, remove and dispose all flashings and counter flashings to substrate.
1.03
RELATED SECTIONS
A.
Section 01010 Summary of Work
B.
Section 01025 Measurement and Payment
C.
Section 01700 Contract Closeout
D.
Section 07540 Thermoplastic Membrane Roofing
1.04
EXISTING CONDITIONS
A. The subcontractor shall verify existing roof construction and square footage.
PART 2 – PRODUCTS
A.
Not used
PART 3 - EXECUTION
3.01
PREPARATION
A.
Protection: 1.
Roofing contractor shall be responsible for protection of property during course of work. Paved areas and building shall be protected from damage. Repair damage at no extra cost to owner. 2. Provide at site prior to commencing removal of debris, a dumpster or dump truck to be located adjacent to the building.
02060-1 DEMOLITION
February 2022